Pembina Advances 932 MW Greenlight Data Centre Power Project with FID

Jul 2, 2026, 10:27 AM EDT1 sourcesAI-analyzed
Why it may matterVerify against the original reporting

Material FID on a large-scale, low-risk project with fixed-price contracts; enhances Pembina's growth trajectory and cash-flow visibility, supporting valuation upside.

AI summary

What happened, with direct paths to the underlying reporting

Pembina, alongside MSIP and Kineticor, secured a final investment decision for the Greenlight Electricity Centre (GLEC), a 932 MW gas-fired plant in Alberta. The project carries an approx. $4.6B total cost with Pembina contributing about $2.1B; ~85% of costs are under fixed-price contracts. Slated for 2H2030 in-service under a long-term tolling agreement, GLEC provides stable, long-dated cash flows and potential expansion opportunities.

  • Pembina announces FID on Greenlight Electricity Centre in Alberta; 932 MW plant.
  • Total project cost ~$4.6B; Pembina net investment ~$2.1B; ~85% fixed-price EPC.
  • GLEC to generate ~$310M annual run-rate EBITDA (net to Pembina); long-term tolling.
  • Ownership: Pembina 47.5%, MSIP 47.5%, Kineticor 5%; ~60% debt, 40% equity.
  • In-service targeted 2H2030; potential expansion via Phase 2 and Alliance Heartland.