Osisko Gold's Cariboo Project Maintains 2029 Gold Pour Timeline

Oct 27, 2026, 7:09 AM EDT1 sourcesAI-analyzed
Why it may matterVerify against the original reporting

Positive progress de-risks the large capex, supports future production expectations, and may lift valuation if milestones remain on track; however, the long lead time to production tempers near-term upside.

AI summary

What happened, with direct paths to the underlying reporting

Osisko Gold Group reports the Cariboo Gold Project remains on track for a Q1 2029 first gold pour and H2 2029 commercial production. As of Sept 30, 2026, the project is ~28% complete with $355 million spent and about $907 million remaining to complete. Engineering is 42% done and over half of procurement packages have been awarded, underscoring ongoing construction momentum and steady execution against the revised plan.

  • Cariboo Gold Project remains on schedule for Q1 2029 first pour; commercial production in H2 2029.
  • As of Sept 30, 2026, project ~28% complete with $355m spent; ~$907m remaining.
  • Engineering ~42% complete; >50% of procurement packages awarded, signaling momentum.
  • Final investment decision announced in September; Osisko emphasizes construction momentum.