FirstEnergy's Potomac Edison advances Gore-Doubs-Goose Creek grid upgrade under regulatory review

Nov 2, 2026, 6:48 PM EST1 sourcesAI-analyzed
Why it may matterVerify against the original reporting

The project expands FE's regulated asset base with multiyear construction and in-service timelines, potentially lifting earnings visibility; however, outcomes hinge on multi-state regulatory approvals and rate-case recoveries.

AI summary

What happened, with direct paths to the underlying reporting

FirstEnergy's Potomac Edison seeks a Virginia CPCN to move forward with the Gore-Doubs-Goose Creek improvements, strengthening the grid across VA, WV, and MD. The project rebuilds about 29 miles of 138 kV lines and adds two new 138 kV runs mostly on existing routes to minimize community impact. Approvals are staged across states, with in-service targeted for 2030 in Virginia.

  • Potomac Edison seeks Virginia CPCN for Gore-Doubs-Goose Creek grid upgrade.
  • Upgrades cover ~29 miles of 138 kV lines in VA, MD, WV.
  • Construction planned to start 2028; VA in-service by Dec 2030.
  • PJM awarded project in 2023; FE expects $36B capex plan.
  • Project uses existing routes to minimize environmental and community impacts.