Consumers Energy Accelerates Underground Power Line Work to Improve Reliability

Nov 9, 2026, 2:04 PM EST1 sourcesAI-analyzed
Why it may matterVerify against the original reporting

The program represents a material capital spending ramp (short-term cash outflow) intended to reduce storm-related outages and recurring storm/tree-trimming costs over time; net long-term operating savings are plausible but depend on execution and regulatory cost recovery.

AI summary

What happened, with direct paths to the underlying reporting

Consumers Energy will convert 67 miles of overhead lines to underground in 2027 and aims to scale to 400 miles/year by 2028 pending regulatory approval, with $160M of projected investment in 2028–29 and a pilot cost of ~$400k/mile.

  • Consumers Energy plans to convert another 67 miles of overhead lines in outage-prone areas to underground in 2027.
  • The company plans to ramp up to 400 miles a year by 2028, pending regulatory approval.
  • Projected investments of $160 million are expected in 2028 and 2029 to support the ramp-up.
  • A 2024 pilot showed undergrounding costs of approximately $400,000 per mile.
  • Consumers Energy completed more than 11 miles so far in 2026 and 10 miles in 2024.