PCGNeutralPG&E undergrounding milestone and plan vs CPUC SPD-37news
Medium materiality6/10

PG&E Achieves 1,500-Mile Milestone in Major Wildfire Safety Undergrounding Effort

Nov 9, 2026, 3:05 PM EST1 sourcesAI-analyzed
Why it may matterVerify against the original reporting

The 1,500-mile milestone materially reduces wildfire ignition risk and improves long-term service reliability for affected customers (supply/demand for reliable electricity). The CPUC proposed cutback is a policy/regulatory risk that could materially limit future permanent risk reduction and alter PG&E's long-term capital deployment and outage reduction benefits.

AI summary

What happened, with direct paths to the underlying reporting

PG&E announced it has installed and energized 1,500 miles of underground power lines since 2021, filed a 10-year plan to underground 5,000 miles, and warned a CPUC Proposed Decision could cut eligible undergrounding to ~1,100 miles.

  • PG&E has installed and energized 1,500 miles of underground power lines in high fire-threat districts since launching its undergrounding program in 2021.
  • PG&E filed a 10-year Electrical Undergrounding Plan (EUP) proposing to underground 5,000 miles of powerlines across more than 30 counties.
  • The CPUC's Proposed Decision (SPD-37 Joint IOU Application proceeding) could reduce eligible undergrounding under PG&E's plan from 5,000 miles to approximately 1,100 miles.
  • As of this week PG&E completed 325 miles of undergrounding in 2026 and listed recent communities now served by underground lines.