i-80 Gold Announces Positive Preliminary Economic Assessment on the Granite Creek Open Pit Project, Nevada; After-Tax NPV(5%) of $421 Million with an After-Tax IRR of 30% at US$2,175/oz Au
1. i-80 Gold announces a PEA for Granite Creek Open Pit Project. 2. Project shows potential for 130,000 ounces gold production annually. 3. Estimated cash costs around $1,185 per ounce; significant cash flow projected. 4. Internal Rate of Return (IRR) estimated at 30% based on $2,175/oz gold. 5. Expecting efficient permitting process due to existing underground infrastructure.