Tailings Storage Facility No. 3 and New 1,500 tonne per day Mill Expansion Completed and in Operation at Ying Mine, China
1. TSF No. 3 completed on time and under budget, enhancing operational capacity. 2. New flotation line boosts milling capacity to over 1.3 million tonnes per year. 3. Cost reduction achieved; TSF No. 3 construction cost was $28 million, below $38 million budget. 4. Commissioning of new production line enables increased silver-lead, zinc, and copper concentrate output. 5. Ongoing projects position Silvercorp for future growth and increased shareholder value.